Integrated Technical Advisory Services for Indonesia’s National Road Rehabilitation Program
As part of Indonesia’s nationwide effort to modernize and maintain its road network, this project provides technical advisory services to support the implementation of an ADB‑funded rehabilitation and maintenance program across seventeen provinces. Through strategic planning support, engineering guidance, capacity building and rigorous project oversight, Dorsch strengthens the Ministry of Public Works in managing civil works, advancing road sector policies and enhancing long‑term institutional capabilities for road and bridge infrastructure.
The principal objective of the Road Rehabilitation Sector Project is to support the Government of the Republic of Indonesia in implementing the civil works program under an ADB‑funded Road Rehabilitation (Sector) Project in Indonesia, covering seventeen provinces.
Another objective of the Project is to assist the Republic of Indonesia in reformulating and implementing its road sector policies. The Project also aims at building the capacity of the Republic of Indonesia in road and bridge works through provision of training and transfer of knowledge.
The Civil Works components under the Project include:
- Periodic Maintenance Subprojects, consisting of single or double layer asphaltic concrete overlays and associated repair of roadway shoulders, pavement markings and minor drainage works for about 2,500 kilometers of national and provincial roads.
- Road Betterment Subprojects, consisting of civil works for improvements and additions to surface and subsurface drainage, strengthening and minor widening (i.e. widening within the existing right of way) of pavement and shoulders, resurfacing, pavement markings, and signing for safety improvements for about 500 km of the Roads.
- Rehabilitation or replacement of deficient bridge structures on the road sections selected for better mentor periodic maintenance for about 3,000 linear meter of bridges. It included the Srandakan-Brückein Yogyakarta with length of 625 m.
Disziplinen
- Straßen
Gesellschaften
Dorsch Consult asia Co., Ltd.
Auftraggeber
Ministry of Public work, Government of the Republic of Indonesia
Dauer
Von 2002 bis 2007
Standort
Indonesia , Indonesien
Projektleistungen
CTC technical services provided by Dorsch Consult asia include:
- Assisting in the preparation of planning, programming, and budgeting of sub projects to be included in the project using standard procedure and latest version of IIRMS-2000 and BMS.
- Assisting in the preparation of guidelines for the detailed engineering design which will be done by DFTs in order to minimize the design and cost changes during construction (ADB require not more than 20% of the contract value). The guidelines should focus on the improvement of the quality of design input.
- Ensuring that procurement of goods, works and consultant services uses standard documents and follows Bank guidelines, particularly with regard to pre-qualification, short listing and bid evaluation;
- Assisting in the preparation and maintenance of a detailed project implementation schedule for all project components including key activities to be undertaken, and key milestones to be achieved in accordance with the Loan Agreement;
- Advising on alternative courses of action when physical or financial progress towards project outputs deviates from agreed targets and limits;
- Monitoring of the implementation of guidelines and standard operating procedures related to project components, including Quality Assurance Procedures and environmental mitigation and management measurements as defined in the Environmental Management Plan (EMP);
- Establishing, maintaining and monitoring a uniform project accounting system for preparation, consolidation and auditing of Project accounts;
- Coordination of all consultancy services supported by the Project;
- Reporting to the steering committee as required on any problems that a rise during the execution of the projects; and