New Niederfinow North ship lift

The new Niederfinow North ship lift enables larger inland waterway vessels to pass quickly over the 36 m difference in elevation on the Oder-Havel Canal. The trough covers the difference in elevation in three minutes and expands the usable transport capacity of the Havel-Oder Waterway.

The old ship lift, in operation since 1934, was too small for modern coasters and container ships. It formed a bottleneck because the vessels could not pass through or make full use of their cargo capacity; at the same time, annual throughput of around 4.4 million tonnes of freight towards Berlin was expected.

Together with partners, KREBS+KIEFER prepared the feasibility study and carried out structural checking. IRS Stahlwasserbau Consulting AG designed the steelwork and mechanical engineering, including the detailed design for the mechanical engineering. These services supported the technical implementation from design through to commissioning.
 

Elevated side view of the new Niederfinow ship lift with its access bridge, grass-covered embankments and the adjoining canal.

Disciplines

  • Water
  • Hydraulic Engineering

Companies

KREBS+KIEFER Ingenieure GmbH

IRS Stahlwasserbau Consulting AG

Client

Berlin Waterways Construction Authority

Duration

Until 2022

Location

Niederfinow, Brandenburg, Oder-Havel Canal, Germany

Project Activities

  • Feasibility study with partners (1998–2000)
  • Steelwork and mechanical engineering design by IRS (2003–2006)
  • Checking of the design with partners (2004–2006)
  • Technical checking across geotechnical engineering, concrete structures, steelwork, mechanical engineering and fire safety
  • Checking of the electrical and control systems, earthworks and temporary works
  • Structural stability checking of the entire load-bearing structure and erection stages
  • Checking of the detailed design (2008–2022)
  • Detailed design for the mechanical engineering by IRS, including the trough drive, trough safety system and closures (2010–2021)
  • Sample-based construction monitoring

Impact

  • Lifting and lowering vessels through a 36 m height difference in three minutes
  • Passage of inland vessels weighing up to 2,300 tonnes
  • Capacity for 104 standard containers rather than 27 on a modern motor cargo vessel
  • Minimal energy demand for lifting due to the balance between trough and counterweights
  • Start of operations 10/2022 after 14 years of construction; designed for a service life of more than 80 years
  • Ecological compensation through near-natural mixed forests, protected biotopes, vegetated embankments and removed barriers

Awards

  • Nomination for the German Civil Engineering Award 2024

     

Contributing to the UN Sustainable Development Goals

We are committed to making a positive impact and supporting the UN Sustainable Development Goals (SDGs). This project contributes to the following SDGs:

Industry, innovation and infrastructure
Life below water
Partnership for the goals

Companies

Project Images

Overview of the new concrete ship lift and the historic steel ship lift standing side by side in Niederfinow.
Front view of the new Niederfinow ship lift with a passenger vessel and a small boat in the basin in front of the structure.
Low-angle view of the tall concrete supports, glazed towers, yellow steel girders and vertical cables of the new Niederfinow ship lift. Niederfinow_K+K_1.JPG